Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 8C, sun and cloud, late showers
Work done today:
- Initial work in placing the root barrier between the 244 and 248 buildings
- Initial work in placing the root barrier behind the 244 building
- Metal flashing completed on patios
- Workers onsite: At least four observed
The root barrier is a thick, cloth-like cover that is permeable to allow moisture through, but with a fine mesh designed to inhibit roots from penetrating. It is laid on top of the membrane to protect it from any plants or trees growing above.