Phase 1 Membrane Project, Day 87 (December 12, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 8C, drizzle and cloud, some showers

Work done today:

  • More pavers returned to the patios. At this point, all five patios have the majority of the pavers restored. The boarding and stone cladding work remains to be done.
  • Workers onsite: At least four.