Phase 1 Membrane Project, Day 76 (November 29, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, overcast

Of the five Saturdays in November, this is the only one when work was performed onsite.

Work done today:

  • Membrane applied to concrete lip along affected patios.
  • Membrane extended along the base of the 244 and 248 buildings and pillars.
  • Workers onsite: At least 4.