Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 14C, mostly cloudy
No work done today.
NOTE: The cracks in the concrete slab were repaired with Kryten Krystol compound. The material needs to cure/dry before the new membrane can be applied, so no work on the concrete slab will happen for what is likely to be at least a few more days, depending in part on the weather.
The site today, November 10th:
