Phase 1 Membrane Project, Day 58 (November 7, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 11C, mix of rain and cloud

Work done:

  • Wooden forms removed from concrete curb.
  • Plastic sheets removed from crack repairs on the concrete slab.
  • Workers onsite: At least two.

Also:

  • Delivery of multiple shrink-wrapped palettes. I’m unsure of the contents, but it is possible it is membrane material, as installation of the new membrane is close now.
  • Strata Engineering had people inspecting the site.