Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 6C, cloudy
No work onsite today.
I believe there are discussions happening between various parties over certain items (how vague, I know) and we probably won’t see much happening onsite until the discussions are complete.