Phase 1 Membrane Project, Day 129 (February 9, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, showers

No work onsite today.

The biweekly meeting was held onsite today with representatives from:

  • Prostar
  • Strata Engineering
  • Quay Pacific
  • Copperstone Council (represented by the Vice President)