Phase 1 Membrane Project, Day 124 (February 3, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 12C, cloudy

No work onsite today.

I don’t have anything official to back this up, but based on the work completed and some designs that are pending approval, we may not see any workers onsite for a few days.

From Update 5, which should be going out to owners soon, here’s what’s left for the project:

  1. Drainage work around the ventilation shaft.
  2. Allan block wall to be re-assembled behind the ventilation shaft.
  3. Membrane design for the three pipes on the south side of the 248 building.
  4. Filling the excavation at the end of the walkway to allow access to the stairs leading to the hospital lane. This will be a temporary design until Phase 2 begins (design is under review).
  5. Replacement of spray insulation that has fallen in the parkade.
  6. Repairing cracks in the parkade ceiling in areas noted by Strata Engineering.

On #4, workers have created a temporary bridge over the open area, allowing residents and visitors to access the stairway leading up to the hospital lane.