Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 10C, heavy rain
No work onsite today, though this is likely due to the heavy rain.
One thing I neglected to mention from before is the two light posts between the 244 and 248 buildings were recently reconnected to the electrical system, so they are working again.
The site today, during the day and then shortly after sunset, showing the lights now working: