Phase 1 Membrane Project, Day 121 (January 29, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, rain and cloud

Work done today:

  • Topsoil distributed over the majority of the worksite
  • Workers onsite today: Six