Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 11C, cloudy
Work done today:
- Stone (gravel) was placed around the ventilation shaft by the 244 building, and an aeration mat was also put in place, though it may not be resting on clean material (this may change, possibly)
- Perforated pipes were extended out of drains where soil will be placed, to facilitate proper drainage through the soil
- Additional Allan blocks were put in place
- The aeration mat has been taped down in more areas
- A load of sand/light soil was delivered. This will be the base layer for the soil.
- Workers onsite: Four