Phase 1 Membrane Project, Day 118 (January 26, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 5C, cloudy

Work done today:

  • Mastick (sealant) material applied to the sides of the ventilation shaft at the northwest corner of the 244 building, in preparation for gravel and overburden (soil) being placed.
  • Workers onsite: At least two.

Today was also the biweekly meeting between all parties:

  • Strata Engineering
  • Prostar
  • Copperstone Council (represented by the Vice President)
  • Quay Pacific

A report on current work will be sent from council to owners soon.

NOTE: At today's meeting, Prostar claimed their absence over most of the previous week was to allow the irrigation team to complete their work.