Phase 1 Membrane Project, Day 117 (January 24, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 6C, sunny

Work done today:

  • Completion of the gravel being reinstated between the 244 building and wooden beams
  • Continued work on pavers for sidewalk leading to the metal staircase
  • Additional extension of Allan blocks that will form the two planters between the 244 and 248 buildings
  • Additional fit and finish work on patio pavers
  • Workers onsite: Four