Phase 1 Membrane Project, Day 116 (January 23, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 8C, sunny

Work today:

  • Gravel is being moved in place between the 244 building and wooden beams
  • Workers onsite: Four

Leave a Comment