Phase 1 Membrane Project, Day 115 (January 22, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 6C, mostly cloudy

No work onsite today.

Prostar management was looking at the work area today. I am unsure if all four people were from Prostar or if some may have been contractors or from Strata Engineering. In any case, this now marks six of the last seven days when no work has been done on the membrane project.