Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 8C, sunny
Work onsite today:
- New Allan blocks were delivered via WCI Contracting Ltd. and are being placed primarily as the top layer along the sidewalk leading to the staircase.
- Workers onsite: At least two.