Phase 1 Membrane Project, Day 108 (January 14, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 9C, cloudy, some light showers

Work done today:

  • One worker was observed with a blowtorch between the 244 and 248 buildings. I was not able to ascertain what was being done.
  • More material, mainly PVC piping, was also brought in by the irrigation contractor.