Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 9C, cloudy, some light showers
Work done today:
- One worker was observed with a blowtorch between the 244 and 248 buildings. I was not able to ascertain what was being done (or which company they were part of). UPDATE: It appears they placed protective material on the bases of the two lamp posts in the area.
- More material, mainly PVC piping, was also brought in by Blue Drop, the irrigation contractor.