Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 9C, rain
Work done today:
- Remediation work to address deficiencies began today. This covers the root barrier, aeration mat, certain materials and more.
- Work began on assembling the double stack of wooden beams between the 244 and 248 buildings.
- The biweekly meeting took place onsite, with representatives of the following attending:
- Strata Engineering
- Prostar
- Copperstone Council (represented by the Vice President)
- Supervisor for Prostar workers
- Initial setup on the replacement irrigation system began with a separate contractor, mostly staging equipment and material.