Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 4C, clouds and light rain
Work done today:
- The start of cutting and placement of the wooden beams that will form a perimeter around the back (west) and north side of the 244 building. The area between the beams and the building will be filled with gravel, as it was prior to construction.
- Workers onsite today: At least four.