Phase 1 Membrane Project, Day 101 (January 6, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 6C, showers

Work done today:

  • More work on the metal flashing around the base of the 244 building
  • Additional work may have been done, but is not visible
  • Workers onsite: At least two