Phase 1 Membrane Project, Day 100 (January 5, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, clouds, some sun

Work done today:

  • More work on installing the metal flashing along the base of the 244 building
  • Workers onsite: At least two
  • Strata Engineering was also onsite for inspection

Leave a Comment