Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 7C, clouds, some sun
Work done today:
- More work on installing the metal flashing along the base of the 244 building
- Workers onsite: At least two
- Strata Engineering was also onsite for inspection