Phase 1 Membrane Project, Day 96 (December 23, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/
NOTE: Work on the membrane project will be on hold over the Christmas holiday. It will resume on January 3, 2026, with completion of the project expected before the end of January.

More details on the remaining work will be posted soon.

Weather: 6C, cloudy

Today was supposed to be the first day of the holiday break for Prostar, but workers were back onsite.

Work done today:

  • Additional clean-up of area.
  • Metal flashing applied along the base of the stone-clad pillars on the 244 building.
  • Workers onsite today: At least five.

Leave a Comment