Phase 1 Membrane Project, Day 95 (December 22, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, clouds and showers

Work done today:

  • More Allan blocks placed between the 244 and 248 buildings to re-establish the planters.
  • The reglet cut along the concrete curb was widened to bring it up to spec.
  • Gravel and other material were cleaned out of the four central parking spaces, meaning all parking stalls in visitor parking are again available.
  • Workers onsite: At least five.

Leave a Comment