Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 7C, clouds and showers
Work done today:
- More Allan blocks placed between the 244 and 248 buildings to re-establish the planters.
- The reglet cut along the concrete curb was widened to bring it up to spec.
- Gravel and other material were cleaned out of the four central parking spaces, meaning all parking stalls in visitor parking are again available.
- Workers onsite: At least five.