Phase 1 Membrane Project, Day 94 (December 20, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 6C, rain, some clouds

Work done today:

  • Setting Allan blocks along the pavers for the sidewalk leading to the staircase. The blocks will form the planters that were previously located here.
  • Added wooden beams around vertical pipes adjacent to the 248 building.
  • Membrane material applied to concrete pads at the base of the staircase.
  • Workers onsite: At least two.

Leave a Comment