Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 6C, rain, some clouds
Work done today:
- Setting Allan blocks along the pavers for the sidewalk leading to the staircase. The blocks will form the planters that were previously located here.
- Added wooden beams around vertical pipes adjacent to the 248 building.
- Membrane material applied to concrete pads at the base of the staircase.
- Workers onsite: At least two.

