Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 6C, clouds and intermittent light showers
Work done today:
- Steps on staircase to hospital path were reconnected to staircase.
- Metal flashing applied to the south wall of the 248 building.
- Wooden beams brought in, but not yet placed.
- A strip of gravel forming a base has poured between the 244 and 248 buildings, with the most of the pavers forming the sidewalk to the staircase laid on top.
- The large waste bin in the visitor parking lot has been removed.
- Workers onsite: At least four.


