Phase 1 Membrane Project, Day 93 (December 19, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 6C, clouds and intermittent light showers

Work done today:

  • Steps on staircase to hospital path were reconnected to staircase.
  • Metal flashing applied to the south wall of the 248 building.
  • Wooden beams brought in, but not yet placed.
  • A strip of gravel forming a base has poured between the 244 and 248 buildings, with the most of the pavers forming the sidewalk to the staircase laid on top.
  • The large waste bin in the visitor parking lot has been removed.
  • Workers onsite: At least four.