Phase 1 Membrane Project, Day 91 (December 17, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 8C, sun and cloud, late showers

Work done today:

  • Initial work in placing the root barrier between the 244 and 248 buildings
  • Initial work in placing the root barrier behind the 244 building
  • Metal flashing completed on patios
  • Workers onsite: At least four observed

The root barrier is a thick, cloth-like cover that is permeable to allow moisture through, but with a fine mesh designed to inhibit roots from penetrating. It is laid on top of the membrane to protect it from any plants or trees growing above.