Phase 1 Membrane Project, Day 90 (December 16, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, rain and clouds

Work done today:

  • More work on patio restoration, including new metal flashing placed along edges.
  • Other preparation for the root barrier that will sit atop the membrane between the 244 and 248 buildings and behind the 244 building.
  • Liquid membrane material applied to the base of the concrete curb. This is the same material used around the drains.
  • Workers onsite: At least three, possibly more.