Phase 1 Membrane Project, Day 89 (December 15, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: !4C, clouds and some clearing

The biweekly site meeting took place virtually today. Attending were:

  • Strata Engineering
  • Prostar
  • Copperstone Council, represented by the Vice-President
  • Quay Pacific, represented by James Jamieson

The fourth membrane report will be sent to owners soon.

Work done today:

  • A reglet cut was made along the concrete curb that was installed on November 5th. This is to prevent any possible cracks from spreading.
  • The first pieces of metal flashing were put back along multiple patios.
  • Workers onsite: At least four.

Leave a Comment