Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: !4C, clouds and some clearing
The biweekly site meeting took place virtually today. Attending were:
- Strata Engineering
- Prostar
- Copperstone Council, represented by the Vice-President
- Quay Pacific, represented by James Jamieson
The fourth membrane report will be sent to owners soon.
Work done today:
- A reglet cut was made along the concrete curb that was installed on November 5th. This is to prevent any possible cracks from spreading.
- The first pieces of metal flashing were put back along multiple patios.
- Workers onsite: At least four.