Phase 1 Membrane Project, Day 86 (December 11, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, cloudy with isolated showers

Work done today:

  • Further work on extending membrane around the lamp posts and base of the staircase between the 244 and 248 buildings.
  • Workers onsite: At least four observed.

Leave a Comment