Phase 1 Membrane Project, Day 85 (December 10, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, heavy rain

There were people onsite today, but I believe it was mostly site inspection and moving some equipment out of the rain or to other areas.