Phase 1 Membrane Project, Day 73 (November 26, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 9C, cloudy

Work done today:

  • Continued work on membrane on the concrete slab between the 244 and 248 buildings.
  • Sweeping, cleaning and drying of the concrete slab behind the 2444 building.
  • Primer applied to most of the area behind he 244 building, in preparation for membrane.
  • Primer applied to lower area of concrete slab between the 244 and 248 buildings (next to the parking lot)
  • Workers onsite: At least four.