Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 11C, some clearing, cloudy
Work done today:
- The first layer of membrane was applied to the concrete slab between the 244 and 248 buildings
- The area behind the 244 building was further cleaned/cleared, primarily using a leaf blower
- Strata Engineering was onsite, others may have been as well
- Workers onsite: At least two observed
View from hospital path showing the first layer of membrane on the concrete slab bwtween the two buildings: