Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 11C, drizzle and light rain
No work onsite today.
Biweekly onsite meeting took place with:
- Strata Engineering
- Prostar
- Copperstone Council, represented by the Vice President
- Quay Pacific had no representation this week due to illness