Phase 1 Membrane Project, Day 60 (November 10, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 14C, mostly cloudy

No work done today.

NOTE: The cracks in the concrete slab were repaired with Kryten Krystol compound. The material needs to cure/dry before the new membrane can be applied, so no work on the concrete slab will happen for what is likely to be at least a few more days, depending in part on the weather.

The site today, November 10th: