Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 11C, mix of rain and cloud
Work done:
- Wooden forms removed from concrete curb.
- Plastic sheets removed from crack repairs on the concrete slab.
- Workers onsite: At least two.
Also:
- Delivery of multiple shrink-wrapped palettes. I’m unsure of the contents, but it is possible it is membrane material, as installation of the new membrane is close now.
- Strata Engineering had people inspecting the site.