Phase 1 Membrane Project, Day 54 (November 3, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 11C, high cloud and filtered sun

The fifth biweekly status meeting took place mid-morning. Attending were:

  • Prostar
  • Strata Engineering
  • Sub contractor reps
  • Copperstone Council, represented by the Vice President

Work done today:

  • Continued work on repairing cracks on the concrete slab using Kyrton grout material
  • Workers onsite: At least two observed