Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/
UPDATE: This post originally said no work was performed. It has been updated to correct this.
Weather: 10C, heavy rain for most of the day
Work done today:
- At least one crack in the underground parkade ceiling was repaired using Kryton grout material.
- Workers onsite: Unknown.