Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 10C, showers and clouds
Work done today:
- No work observed around the concrete slab behind the 244 building or between the 244 and 248 buildings.
- Some preliminary work for the new replacement drains was apparently done in the 244 parkade early in the evening (plumbers were observed in the area).
The site as of Tuesday, October 28, 2025:

