Phase 1 Membrane Project, Day 48 (October 27, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, clouds and showers

Work done today:

  • Additional removal of stone cladding from several pillars adjacent to the 244 building patios.
  • Wood forms moved in place near the retaining wall behind the 244 building (the area is not clean/ready for a concrete pour, so this may just be temporary).
  • Workers onsite: 3 observed, possibly more.