Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 10C, clouds and showers
Work done today:
- Additional removal of stone cladding from several pillars adjacent to the 244 building patios.
- Wood forms moved in place near the retaining wall behind the 244 building (the area is not clean/ready for a concrete pour, so this may just be temporary).
- Workers onsite: 3 observed, possibly more.
