Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
Weather: 13C, heavy rain and wind
Work done today:
- Removal of planking along the bottom of the 244 building on the west and north sides.
- Removal of the lower portion of stone cladding from the pillars in the areas listed above.
- This work is being done to allow the new membrane to extend eight inches (about 20 cm).
- Workers onsite today: At least four observed.
- Strata Engineering also had at least four people onsite doing inspections.