Phase 1 Membrane Project, Day 45 (October 24, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/

Weather: 13C, heavy rain and wind

Work done today:

  • Removal of planking along the bottom of the 244 building on the west and north sides.
  • Removal of the lower portion of stone cladding from the pillars in the areas listed above.
    • This work is being done to allow the new membrane to extend eight inches (about 20 cm).
  • Workers onsite today: At least four observed.
  • Strata Engineering also had at least four people onsite doing inspections.

Leave a Comment