Phase 1 Membrane Project, Day 39 (October 17, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/

Weather: 14C, sunny, some clouds

Work done today:

  • Continued removal of membrane (apparently using a power washer of some type).
  • Removal of stone cladding along bottom edge of building in preparation for extended membrane application, using a hammer and chisel.
  • Workers onsite: At least 2 observed