Phase 1 Membrane Project, Day 32 (October 7, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 17C, sun and cloud

Work done today:

  • Continued stripping of membrane behind the 244 building using the Terminator (yes, that is what the machine is called)
  • Workers onsite: 3-5