Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
Weather: 17C, sun and cloud
Work done:
- Completed removal of membrane from all patios that are part of Phase 1 (five total)
- Tested equipment and did partial removal of membrane in open area
- Workers onsite: At least three