Phase 1 Membrane Project, Day 28 (October 3, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/

Weather: 17C, sun and cloud

Work done:

  • Completed removal of membrane from all patios that are part of Phase 1 (five total)
  • Tested equipment and did partial removal of membrane in open area
  • Workers onsite: At least three