Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 18C, cloudy, showers in early morning
No work onsite today.
NOTE: Currently work is not being done on Saturdays, though under city permit, it is allowed. I am including Saturdays to avoid confusion about what is happening on those days.