Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
Weather: 21C, sunny
No work onsite today.
NOTE: Prostar is not working on Saturdays at this point. I am including Saturdays, as they are allowed under permit to work on them if they choose, and this addresses possible confusion on why work may not be happening.