Phase 1 Membrane Project, Day 15 (September 16, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/

Weather: 29C, sunny

Work done today:

  • Further plumbing work on the three new drains done by Highmark Plumbing

Leave a Comment