Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
Weather: 24°C, hazy sun, brief late afternoon showers
Work done today:
- Aeration membrane pieces removed. These rubber “mats” sit above the membrane. They had been previously piled into the flower bed between the 244 and 248 buildings and have now been disposed of.
- All wooden beams have now been disposed of (UPDATE: I have confirmed the wooden beams were loaded into a truck and removed from the site).
- The stone wall that forms tier 1 of the retaining wall was power-washed.
- The pavers from the south-most patio facing the retaining wall have been temporarily removed.
- New plywood!
Workers onsite: Two observed doing the washing, four others loaded and removed the wooden beams.