Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
Weather: Mostly sunny, 25°C
No work onsite today.
I will try to find out if work will be happening on Saturdays as the project continues and update here when I learn more.