Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 20C, sunny
The third biweekly status meeting took place. Attending were:
- Prostar
- Strata Engineering
- Sub contractor reps
- Copperstone Council, represented by the Vice President
- Quay Pacific strata property manager
Prostar indicated all membrane should be removed by the end of this week.
Work done today:
- Membrane removed from the area between 244 and 248 buildings.
- Excavation done at edge of visitor parking adjacent to the above area. This also acts as a preview of the work that will be required for Phase 2.
- Workers onsite: Between 3-5
