Phase 1 Membrane Project, Day 30 (October 6, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/

Weather: 20C, sunny

The third biweekly status meeting took place. Attending were:

  • Prostar
  • Strata Engineering
  • Sub contractor reps
  • Copperstone Council, represented by the Vice President
  • Quay Pacific strata property manager

Prostar indicated all membrane should be removed by the end of this week.

Work done today:

  • Membrane removed from the area between 244 and 248 buildings.
  • Excavation done at edge of visitor parking adjacent to the above area. This also acts as a preview of the work that will be required for Phase 2.
  • Workers onsite: Between 3-5